Transient hydraulic assessment for the bid design of a 585 km potable water transmission pipeline.

Illustrative pipeline-construction photograph with a yellow pipe-layer and workers in a trench, adapted to landscape with subtle blue effects.
Illustrative pipeline construction · Photo courtesy RTCC · AI-enhanced

The challenge

The Jubail–Buraydah corridor links eastern water sources with central Saudi Arabia. Its long transmission route, reservoir connections and future branch interfaces require consideration of operating changes and reverse-flow arrangements.

Our contribution

Pipelab’s scope is the transient hydraulic study for bid design. The overall project comprises a 585 km pipeline with diameters from 72 to 96 inches, connections to Rafiah and Asiaah, and provisions for future supply points.

Engineering outcome

The study supports the bid-stage assessment of hydraulic behaviour and the engineering basis for a long-distance supply corridor with planned operating flexibility.

585 kmmain transmission pipeline
72″–96″pipeline diameter range

Figures describe the project’s design scale, not measured operating results.

Next project

Riyadh–Qassim · IWTP

Start a conversation

Your next challenge.
Our next conversation.

Discuss your project
Pipelab GmbH · Swiss Headquarters

Zurich

Technoparkstrasse 1
8005 Zurich
Switzerland

Pipelab Middle East · Subsidiary

Riyadh

Servcorp · Olaya Towers, B, L25&28
Olaya St / Mohammed bin Abdul-Aziz St
Riyadh, Saudi Arabia

www.pipelabarabia.com
Direct contact

Contact

info@pipelab.ch
+41 78 716 22 03

↑